Firebox Repairs on a Case 65

By Jon S. Gould
Published on September 1, 1997
1 / 6
Forming die and clamping assembly used to flange corners.
Forming die and clamping assembly used to flange corners.
2 / 6
New mudring assembly shown in comparison to old mudring assembly.
New mudring assembly shown in comparison to old mudring assembly.
3 / 6
Replacement sheet installed, prior to installation of stays.
Replacement sheet installed, prior to installation of stays.
4 / 6
One corner partially flanged. The number indicates ''heat'' number 4 (four) of process.
One corner partially flanged. The number indicates ''heat'' number 4 (four) of process.
5 / 6
6 / 6
New patch installed in crown sheet for fusible plug, prior to installation of stays.
New patch installed in crown sheet for fusible plug, prior to installation of stays.

525 West Van Buren Avenue Naperville, Illinois 60540

The 1993 annual show of the Northern Illinois Steam Power Club
of Sycamore, Illinois, opened with one engine conspicuously absent.
Longtime participant Charlie Fruit of Kirkland, Illinois, and his
65 HP Case engine, Number 35072 were not found in their usual spot
under the oak tree. We learned from Charlie later that day that his
engine had failed its recent biannual state boiler inspection and
would require very extensive repairs to its firebox before it would
be allowed to be fired in public again. This article will tell how
these repairs were made.

In Illinois our hobby boilers are subject to a very rigorous
inspection process that includes hydrostatic, ultrasonic and visual
testing. It was during the hydrostatic test phase that the problem
with Charlie’s boiler was discovered. Water began to leak in
one rear corner of the mudring in the lower ogee curve area. Closer
investigation revealed severe wasting to the entire mudring area
and the state boiler inspector made the decision to fail the
boiler. He did not however rule out the possibility of repairing it
at this time, and Charlie was left with some hope that his engine
would be operable again at some future date. It was at this time
which we became involved. Paul Andermann, Larry Marek and I have
been involved in the repair of several traction engine boilers in
the past, and we became interested in the possibility of repairing
Charlie’s boiler. Over the next several weeks following the
show various plans were discussed with our state inspector, and the
decision was made to move the engine to Wheatland Machine Shop in
Naperville, Illinois. This business is operated by Paul Andermann,
a steam engine man himself, and is the meeting place of many of us
with like interest.

Before a more complete analysis of the condition of the firebox
was possible, it was necessary to remove all of the accumulated
soot and scale which coated the inside of the firebox. This was
done with a needle sealer and it was during this process that it
became apparent just how badly wasted the lower mudring area was,
as we actually broke through the boiler plate in several areas.
These areas were later removed with a torch and a more complete
inspection revealed that the entire lower mudring area was wasted
below allowable limits and would have to be replaced. Our inspector
wanted us to remove all the metal from the second row of staybolts
down. This required removing all 78 rivets and 64 staybolts from
the lower firebox area. The rivets were removed by burning both
heads off and blowing a hole through the center of the rivet almost
to the edge; the rivet was then punched out with a drift. The
staybolts were cut around the edges in the firebox sheets and then
burned back so that the sheets would clear when they were dropped
down. After the lower firebox sheets were removed, the remainder of
the staybolts were cut flush with the inside of the wrapper sheet.
The heads of the staybolts were then burned off on the outside, a
hole was then blown through the center and most of the material was
burned out just to the threads. The remainder was removed with a
sharp chisel.

With the lower firebox sheets removed it was possible to take a
closer look at the inside of the wrapper sheet, throat sheet and
back head. This inspection showed some wasting around the hand hole
openings, at the point where the ogee curve met the outer sheets
and also at the point where the staybolts met the outer sheets. We
were pleased, however, that the outer sheets did not appear to be
as bad as the firebox sheets. At this time our boiler inspector
took another look at the boiler and approved the repair of these
areas with pad welding. Each of these steps were followed by
another inspection and the approval to go to the next phase. I
should add that one of these inspections also found a section of
the crown sheet adjacent to the fusible plug to be thin, so this
too would need to be repaired. After much discussion with the state
inspector regarding the different possibilities for fabricating the
necessary replacement parts, we learned that no modification to the
original design would be allowed. We would have to flange and rivet
the replacement mudring sheets exactly like the original. We had
done several jobs in the past involving flanging replacement boiler
sheets, but this was to be by far the most extensive yet. We were
still fairly innocent at this time and not scared off by hard work,
so we pressed forward.

The first step in this process was to design and fabricate
special dies over which to flange the boiler plate. We found that
the amount of offset in the front and rear ogee curve was
different, so it was determined that two dies (made out of cast
iron) would be required. The patterns for these dies were made out
of wood and with allowance for shrinkage were shaped to provide the
proper radius and offset to bend all four corners of the lower
firebox sheets. Special steel is used in the construction of
boilers and boiler replacement sheets and is tightly regulated by
A.S.M.E. Code. Several sheets of this plate was purchased from
Joliet Boiler & Welding with all necessary documentation in
5/16‘, 3/8‘ and
‘ thicknesses. All these plates were stamped with a number that
could be traced should there be any question regarding their
acceptability for this purpose. The dies were mounted on a heavy
steel fixture table with a sturdy hydraulic clamping device to hold
the plates during the actual flanging process. It must be
remembered that the dies were only to be used for flanging the
corners of the ogee curve area; the other areas of this curve could
be formed on a heavy press brake. After this was done, it was time
to start on the corners. Before it is possible to work this heavy
plate by hand, however, it is necessary to heat it to a bright
orange color. This was done in a large coal forge owned by Larry
Marek. As the plate to be flanged was being heated, we preheated
the die with a rosebud tip. We did not want this four hundred pound
piece of cast iron drawing all the heat out of the sheet. After the
sheet was brought up to the proper heat, it was quickly moved to
the die and clamped into place. The actual flanging then was
accomplished by bending the plate over the die with sledgehammer
blows with several people at once swinging before the heat left the
piece. This process was repeated about seven times before the sheet
conformed to the required shape. This flanging required very heavy
labor and many Saturdays before it was complete.

Online Store Logo
Need Help? Call 1-866-624-9388